Sample report

Kitchen + one bathroom, 4-room HDB resale flat, three quotations. Names removed; numbers are illustrative.

Summary. Quote B looks cheapest at S$14,900, but it leaves out waterproofing, electrical work and the HDB permit. Quote C hides hacking and tiling inside a "Kitchen package" with no quantities. Quote A is the most complete but asks for 50% at signing. Before choosing, ask B and C to add the missing lines, and ask A to move to a staged payment schedule.

1. Side-by-side breakdown

Item (normalised)Contractor AContractor BContractor CWhat to ask
Hacking: kitchen wall tiles + floor screedS$1,450S$1,200in "Kitchen package"C: split the package into lines with quantities.
Kitchen wall tiling (supply + lay)S$2,100 (18 m²)S$1,980 (no area stated)in "Kitchen package"B: state the m² and the tile allowance per m².
Bathroom waterproofing + 24h ponding testincluded, 5-yr warrantymissing"waterproofing" onlyB, C: membrane brand, coats, ponding test, warranty in writing.
Carpentry: kitchen cabinetsS$4,200 (14 ft run)S$3,600 ("top + bottom")S$5,100 (16 ft)Normalise per foot run, carcass material, hinges, laminate.
Electrical: 6 power points, 4 lighting pointsS$880missingS$950B: is electrical excluded? Who is the licensed electrical worker?
HDB renovation permit (if hacking / tiling over)contractor appliesnot mentionedcontractor appliesAll: confirm HDB DRC listing and who applies for the permit.
Disposal + protection of common areasS$350S$300missingC: is debris disposal included?
Total quotedS$18,400S$14,900S$19,800B is cheapest because 3 items are missing; add them back before comparing.

2. Missing or vague

3. Permit and licence questions

4. Payment schedule to propose

StageQuote A asksSchedule to proposeRelease when
Signing50%10%Signed contract with itemised quote + drawings
After hacking + permit-20%Hacking done, debris cleared, permit copy received
After wet works40%30%Tiling + waterproofing done, ponding test photo
After carpentry installed-30%Cabinets installed, matches drawings
Handover + defects fixed10%10%Defect list closed, warranties in writing

The idea: at any point, the money you have paid stays close to the value of work actually done. You and your contractor agree the final terms.

5. Questions to send (Contractor B)

Hi, thanks for the quotation. Before we decide, could you confirm:
1. Is bathroom waterproofing included? Which membrane, how many coats, is there a 24-hour ponding test, and what is the warranty?
2. Is electrical work included? If not, what would 6 power points and 4 lighting points cost?
3. Will you apply for the HDB renovation permit, and are you listed in HDB's Directory of Renovation Contractors?
4. What is the m² and tile allowance for the kitchen wall tiling?
5. Can we pay 10% at signing and the rest in stages as each part is completed?
6. What is the target completion date?